Hydro-Québec · Awarded contract
Awarded

Addition of 4th Transformer and Protection System Upgrade at Chaudière Substation

Awarded 10 Aug 2026

View live tenders
Awarded10 Aug 2026
Value$8,131,012.99
ProvinceQuebec
CategoryEnergy & Environment
Expires in 1y 10mo2y 1mo term, 13% elapsed
Awarded 10 Aug 2026Expires 10 Sept 2028

Hydro-Québec awarded a contract to Construction St-Arnaud Inc.

for the addition of a fourth transformer and the renewal/modernization of the 61850 protection system at the Chaudière substation in the Chaudière-Appalaches region, operating at 230-25 kV.

The contract, valued at CAD 8,131,012.99, covers non-residential building construction work.

Similar open tenders12

GovMarket

We do the hard work.
You win the work.

We find the tenders, read the documents and track who wins, so your time goes on bids you can win.

–open energy and environment tenders right now
–new in the last 7 days
–contracts awarded in the last 12 months
7 days free, then $59/CAD per month

You're In — Free Trial Activated

You now have full access to GovMarket Premium for 7 days. You’ll be charged at the end of the trial unless you cancel.

  • Tell Us What You Do — We'll surface the tenders that are most relevant to your business.