Installation of 120kV Underground Conduit for Circuit L1210 between St-Maxime and Marie-Victorin Substations
Hydro-Québec · Awarded contract
AwardedInstallation of 120kV Underground Conduit for Circuit L1210 between St-Maxime and Marie-Victorin Substations
Awarded 05 Jun 2019
Awarded05 Jun 2019
Value$4,784,555.45
SupplierEnvironnement Routier NRJ Inc .
AgencyHydro-Québec
ProvinceQuebec
CategoryEnergy & Environment
Ended 7y 3mo ago3mo term
Awarded 5 June 2019Expired 5 Sept 2019
About
Hydro-Québec awarded a contract to Environnement Routier NRJ Inc.
for the installation of 120kV underground conduit for circuit L1210 between the St-Maxime and Marie-Victorin substations in the Montérégie region.
The contract, valued at CAD 4,784,555.45, falls under the category of construction of infrastructure or civil engineering works.
Similar open tenders12
TenderCloses
ECI Construction of New 315-25 kV Substations Toupin and SoulignyInfrastructure
21 Jan 2027
Construction of New 230 kV Sectioning Substation — Poste Pierre-Laporte, MontérégieEnergy & Environment
20 Jan 2027
Montréal — Poste Des Sources (315/25 kV): Travaux de pérennité et mise à niveauEnergy & Environment
18 Dec 2026
Construction of Lionel-Groulx Step-down SubstationInfrastructure
03 Dec 2026
Mise à niveau des équipements électriques — Sous‑station Est et Ouest, station d’épuration Jean‑R. MarcotteWater & Sanitation
08 Dec 2026
Underground Infrastructure Works 2027 — Sewer Rehabilitation by Lining on Various Streets, City of LavalWater & Sanitation
01 Dec 2026
Supply and Installation of 600 V, 400 A Electrical Services, Electric Heating and Ventilation at La Grande‑Rivière Airport Garage and km 600 Garage – Route Billy‑DiamondConstruction
20 Nov 2026
Installation of Electric Vehicle Charging Stations at 1001 St-Laurent Street West, LongueuilEnergy & Environment
11 Dec 2026
Modifications and Additions to Municipal Underground Conduit Network on Avenue Beaumont (Wiseman to d’Outremont)Infrastructure
01 Dec 2026
Rehabilitation of Nicolet Outfall between Rue Notre‑Dame Est and the St. Lawrence RiverWater & Sanitation
26 Nov 2026
Separation of Networks on Rue Monseigneur-Prévost (Saint-Marc to Saint-Laurent) — Sewer ConstructionWater & Sanitation
14 Jan 2027
Replacement of Culverts 121690 and 159305 Using Trenchless Technique on A-15 at Prévost (Laurentides)Infrastructure
26 Nov 2026
GovMarket
We do the hard work.
You win the work.
We find the tenders, read the documents and track who wins, so your time goes on bids you can win.
–open energy and environment tenders right now
–new in the last 7 days
–contracts awarded in the last 12 months
7 days free, then $59/CAD per month
Revenue from government work$312K won so far