Reconfiguration of Core Lab Phase 2 and Ventilation System Upgrade at Hôpital Maisonneuve-Rosemont
Santé Québec - Établissement CIUSSS de l’Est-de-l’Île-de-Montréal · Awarded contract
AwardedReconfiguration of Core Lab Phase 2 and Ventilation System Upgrade at Hôpital Maisonneuve-Rosemont
Awarded 29 Apr 2021
Awarded29 Apr 2021
Value$1,644,517.89
SupplierLes Constructions Berka Inc.
ProvinceQuebec
CategoryConstruction
Ended 4y 7mo ago1y term
Awarded 29 Apr 2021Expired 29 Apr 2022
About
Santé Québec - Établissement CIUSSS de l’Est-de-l’Île-de-Montréal awarded a contract to Les Constructions Berka Inc.
for the reconfiguration of the Core Lab Phase 2, including replacement of the analytical chain and upgrading the VA-6 ventilation system to standards at Hôpital Maisonneuve-Rosemont.
The contract value is $1,644,517.89.
Similar open tenders12
TenderCloses
Ventilation Compliance Upgrade — École de l'Harmonie, Saint-EdouardConstruction
01 Dec 2026
Air Conditioning and Ventilation Modifications at Jean-Bouchard Amphitheatre, Saint‑JanvierConstruction
26 Nov 2026
On-Demand Contract for Capital Works and Medical Equipment Installation — HEJ, HSFA, HSS & Santé Québec HQ (CHU de Québec – Université Laval)Construction
01 Dec 2026
Installation de nouvelles chaudières — chaufferie de l'ancien hôpital Royal Victoria, 687 avenue des Pins Ouest, Montréal (Phase B)Construction
23 Nov 2026
Upgrade of Ventilation Systems – Polyvalente La Frontalière, CoaticookConstruction
25 Nov 2026
Addition of Tempered Ventilation, Building Envelope Repairs and Interior Reconfiguration — École Mgr Feuiltault, Sainte‑MarieConstruction
08 Dec 2026
Replacement and Modernization of Corridor Ventilation, Domestic Hot Water and Garage Heating – 5500 6e Avenue, MontréalConstruction
02 Dec 2026
Laboratory Refurbishment – Centre hospitalier de la MitisConstruction
27 Nov 2026
Montérégie / IREQ Laboratoire Haute Tension – Replacement of Chiller with Air-Source Heat PumpConstruction
04 Dec 2026
HRV Interior Systems for New VIC Project – McGill University (Pavilions A, E, L, N) Lot 0920Construction
02 Dec 2026
Electrical, Telecommunications & Physical Security Works – Charles‑Le Moyne Hospital Operating Room and Day Surgery Expansion, LongueuilConstruction
27 Nov 2026
Renovation of Science Rooms (Phase 1) and EHDAA Sector Level 200 — Polyvalente La Samare, PlessisvilleConstruction
26 Nov 2026
GovMarket
We do the hard work.
You win the work.
We find the tenders, read the documents and track who wins, so your time goes on bids you can win.
–open construction tenders right now
–new in the last 7 days
–contracts awarded in the last 12 months
7 days free, then $59/CAD per month
Revenue from government work$312K won so far