Rehabilitation of Billy-Diamond Road (km 460–538) Including Culvert and Guardrail Replacement
Société de développement de la Baie-James · Awarded contract
AwardedRehabilitation of Billy-Diamond Road (km 460–538) Including Culvert and Guardrail Replacement
Awarded 05 Mar 2026
Awarded05 Mar 2026
Value$61,646,987.70
SupplierEurovia Québec Construction Inc.
ProvinceQuebec
CategoryInfrastructure
Expires in 1y 4mo2y term, 35% elapsed
Awarded 5 Mar 2026Expires 5 Mar 2028
About
Société de développement de la Baie-James awarded a contract to Eurovia Québec Construction Inc.
for the rehabilitation of the roadway, replacement of culverts, and replacement of safety guardrails between km 460 and km 538 of Route Billy-Diamond.
The contract, valued at CAD 61,646,987.7, falls under the category of road infrastructure maintenance and repair.
Similar open tenders12
TenderCloses
Bridge Rehabilitation – Hwy 88 over Wabasca River (Km 51.445), Peace RegionInfrastructure
16 Dec 2026
Road Infrastructure Rehabilitation Works – Îles-de-la-Madeleine (Bas‑Saint‑Laurent–Gaspésie–Îles‑de‑la‑Madeleine)Infrastructure
07 Jan 2027
Water Pipe Rehabilitation, Lead Service Replacement and Road Rehabilitation — chemin de la Côte‑Sainte‑Catherine, avenue Decelles, place Decelles (arrondissement de CDN)Infrastructure
10 Dec 2026
School Crossing Installation and Pavement Rehabilitation on Route 393 - Abitibi-TémiscamingueInfrastructure
07 Dec 2026
Preliminary Design Studies, Plans and Specifications for Route 337 Rehabilitation (A-25 to rue Rodrique) and Culvert 62519 Repair — TerrebonneInfrastructure
07 Dec 2026
Major Rehabilitation of Boulevard Guimond Infrastructure — Roads, Water Pipes, Cables, and Road MarkingsInfrastructure
26 Nov 2026
Pavement Rehabilitation of Boulevard Saint-Jean — south of Boulevard Hymus to Sedgefield AvenueInfrastructure
07 Dec 2026
Redevelopment of Intersections at Chemin de la Bataille Nord‑Sud and Chemin de Fontarabie with Route 104 — La PrairieInfrastructure
19 Nov 2026
Construction of Bridge P-19986 on Route 289 over Rivière Bleue (Rivière-Bleue)Infrastructure
19 Nov 2026
Chemin Champagne Road Rehabilitation and East-side Ditch ReprofilingInfrastructure
23 Nov 2026
Bridge Rehabilitation – Highway 49 over Spirit River at West Boundary of Rycroft (km 34.437)Infrastructure
17 Dec 2026
Rehabilitation of Nicolet Outfall between Rue Notre‑Dame Est and the St. Lawrence RiverWater & Sanitation
26 Nov 2026
GovMarket
We do the hard work.
You win the work.
We find the tenders, read the documents and track who wins, so your time goes on bids you can win.
–open infrastructure tenders right now
–new in the last 7 days
–contracts awarded in the last 12 months
7 days free, then $59/CAD per month
Revenue from government work$312K won so far