Rehabilitation of Lift Stations 3 and 12 in Chestermere, Alberta
Awarded 30 Jan 2026
About
EPCOR Water Services Inc.
awarded a contract to Whitson Contracting Ltd.
for mechanical and electrical installation services for the rehabilitation of Lift Stations 3 and 12 in Chestermere, Alberta.
EPCOR retained prime contractor status and pre-purchased long lead equipment, including a generator for Lift Station 3 and an MCC for Lift Station 12, for free issue to the contractor.
Construction was scheduled to begin in January 2026 with the arrival of the generator and proceed to March 2026 with the arrival of the MCC, with a project end date of November 27, 2026, by which all elements, including commissioning, record management, and invoicing, were to be complete.