Safety Review of Water and Mining Tailings Dams and Geotechnical Investigations at Former Darius-O'Brien Mine Site
Ministère des Ressources naturelles et des Forêts · Awarded contract
AwardedSafety Review of Water and Mining Tailings Dams and Geotechnical Investigations at Former Darius-O'Brien Mine Site
Awarded 03 Jul 2024
Awarded03 Jul 2024
Value$589,737.55
SupplierCIMA+ S.E.N.C.
ProvinceQuebec
CategoryMining & Natural Resources
Ended 11mo ago1y 6mo term
Awarded 3 July 2024Expired 23 Dec 2025
About
Ministère des Ressources naturelles et des Forêts awarded a contract to CIMA+ S.E.N.C.
for a safety review of water and mining tailings dams and geotechnical investigations at the former Darius-O'Brien mine site.
The contract, valued at CAD 589,737.55, falls under dam engineering.
Similar open tenders12
TenderCloses
Geotechnical and Hydrotechnical Engineering Services for Yukon Abandoned Mine Sites – Up to 5 AgreementsEnergy & Environment
07 Dec 2026
Geotechnical Assessment of Former Smoky River Coal Mine – Slope Stability Investigation (Grande Cache, AB)Mining & Natural Resources
18 Dec 2026
Stage II Physical Mine Hazard Investigation and Rehabilitation Planning — Eight Former Fluorite Mines, Madoc, OntarioMining & Natural Resources
12 Jan 2027
Construction and Removal of Clay Dike Closures for Spring Flood Response — Morris and Aubigny, MBInfrastructure
01 Dec 2026
Remediation of Former Baker Patton Mine Site – Engineered Cover System, 31 km East of Flin Flon, ManitobaMining & Natural Resources
10 Dec 2026
Rehabilitation of Physical Hazards at Former Hunt - Cornelius Mine (Bat Gate, Fencing and Access Upgrades)Mining & Natural Resources
07 Dec 2026
Compliance Upgrade Works for Neiges Dam – Réserve faunique des Laurentides, Côte‑de‑Beaupré (X0001423)Infrastructure
12 Jan 2027
Project Management for Soil Remediation at Petit Casimr School Tank Farm and Former Federal School — Northlands Denesuline First Nation, ManitobaEnergy & Environment
27 Nov 2026
Construction and Removal of Clay Dike Closures near Emerson and West Lynne, ManitobaInfrastructure
30 Nov 2026
Sonic Drilling Services for Tailings Sampling – Nigadoo, New BrunswickMining & Natural Resources
04 Dec 2026
Construction and Removal of Clay Dike Closures for Flood Response – St. Jean Baptiste & Letellier, ManitobaInfrastructure
02 Dec 2026
Reconstruction of Underground and Surface Infrastructure on Avenue Lamothe, Morison and Papineau (Phase 1 – Delorme Overflow Basin)Infrastructure
20 Nov 2026
GovMarket
We do the hard work.
You win the work.
We find the tenders, read the documents and track who wins, so your time goes on bids you can win.
–open mining and natural resources tenders right now
–new in the last 7 days
–contracts awarded in the last 12 months
7 days free, then $59/CAD per month
Revenue from government work$312K won so far