Shoreline Erosion Protection at McGregor Reservoir – Phase 3
Awarded 15 Dec 2025
About
Alberta Transportation and Economic Corridors awarded a contract to Ironclad Earthworks Ltd.
for shoreline erosion protection at McGregor Reservoir, Phase 3 (SE8 18-21-4 Property), part of the Carseland Bow River Headworks System.
The work includes approximately 200 m of care of water and turbidity barriers, fish capture and release, site clearing and grubbing, 4,087 m3 of topsoil and subsoil stripping, 4,500 m3 of common excavation, 650 m3 of bedding gravel, 250 m3 of gravel armour, 2,400 m3 of riprap, 30 m of 300 mm diameter pipe, 4,087 m3 of topsoil and subsoil placement, 1,500 m3 of erosion control blanket, 2.0 ha of drill seeding, and fence reinstatement.
The contractor is to supply all materials.
The contract value is CAD 793,374.49, with substantial performance by February 16, 2026, and total performance by May 15, 2026.
Similar open tenders12
GovMarket
We do the hard work.
You win the work.
We find the tenders, read the documents and track who wins, so your time goes on bids you can win.