- City of Calgary awards C$59.2m Green Line guideway to Graham Infrastructure for 28 months.
- They have 11 contracts worth C$153.7m since 2024 in GovMarket records.
- Contract runs May 26, 2026 to Sept. 30, 2028; procured by RFP.
The City of Calgary has awarded Graham Infrastructure LP a C$59.2 million contract to build the 114 Avenue and Barlow Trail elevated guideway for the Green Line LRT over 28 months, according to a notice on the Alberta Purchasing Connection.
The work covers a single elevated guideway of about 570 metres with abutments, piers, straddle bents, precast girders and a bridge deck, excluding piling. It includes MSE walls for approaches, drainage and grading, temporary works, site management and utilities coordination.
GovMarket data shows Calgary and Graham have 11 contracts worth C$153.7 million since 2024 in GovMarket records.
Graham Infrastructure has 19 public sector contracts worth C$302.9 million in GovMarket records since 2017. City of Calgary is its top buyer, with 12 contracts worth C$212.9 million.
The award date is June 29, 2026. The contract runs from May 26, 2026 to Sept. 30, 2028. It was procured through a request for proposal. The notice was published Nov. 10, 2026.
Key facts
* 2026 so far
| Year | Value | Contracts |
|---|---|---|
| 2024 | $337.9m | 186 |
| 2025 | $2.14bn | 392 |
| 2026 | $1.13bn | 336 |
* 2026 so far
| Year | Value | Contracts |
|---|---|---|
| 2024 | $30.0m | 4 |
| 2025 | $115.4m | 6 |
| 2026 | $156.0m | 8 |