Grid Connection Works for Apuiat Wind Farm in Côte-Nord
Hydro-Québec · Awarded contract
AwardedGrid Connection Works for Apuiat Wind Farm in Côte-Nord
Awarded 12 Oct 2023
Awarded12 Oct 2023
Value$16,299,351.60
SupplierG.L.R. INC.
AgencyHydro-Québec
ProvinceQuebec
CategoryEnergy & Environment
Ended 2y 1mo ago1y term
Awarded 12 Oct 2023Expired 12 Oct 2024
About
Hydro-Québec awarded a contract to G.L.R.
INC.
for the connection of the Apuiat wind farm in the Côte-Nord region, specifically in Baie-Trinité and Rivière-Aux-Rochers, involving the installation or maintenance of electrical power systems.
The contract value is CAD 16,299,351.6.
Similar open tenders12
TenderCloses
Integration of Renewable Energy Systems at Centrale de Quaqtaq (Nord-du-Québec) – Lot 2Energy & Environment
19 Nov 2026
Supply and Installation of 600 V, 400 A Electrical Services, Electric Heating and Ventilation at La Grande‑Rivière Airport Garage and km 600 Garage – Route Billy‑DiamondConstruction
20 Nov 2026
SaskPower North–South Transmission Interconnection — Two ~250 km Lines and 230 kV Switching Station, SaskatchewanEnergy & Environment
14 Dec 2026
Install 300 kW Solar Microgrid with BESS and Diesel Generators – 14 Wing Greenwood, NSEnergy & Environment
25 Nov 2026
Road Infrastructure Rehabilitation Works – Îles-de-la-Madeleine (Bas‑Saint‑Laurent–Gaspésie–Îles‑de‑la‑Madeleine)Infrastructure
07 Jan 2027
Supply and Delivery of Miscellaneous Electrical Components to Manitoba Hydro Riel G.S. — Delivery by March 31, 2027Energy & Environment
30 Nov 2026
Replacement of Generator at Centre récréatif Édouard-RivetEnergy & Environment
01 Dec 2026
Supply and Delivery of Cables to Manitoba Hydro Riel G.S. – Delivery by 31 March 2027Infrastructure
27 Nov 2026
Installation of 100 kW Photovoltaic (PV) Solar System – Prince Edward Island National Park (Stage 1 Prequalification)Energy & Environment
26 Nov 2026
Parc national de la Gaspésie – Roof Refurbishment and Rooftop Air Conditioning Unit Replacement at Centre de découverte et de servicesConstruction
03 Dec 2026
Construction of up to 97 km 230 kV Transmission Line from Dorsey Convertor Station to Wash’ake Mayzoon Station — ManitobaInfrastructure
15 Dec 2026
Fabrication of Hot-Dip Galvanized Stilling Well Platform for Pointe-des-Cascades Hydrometric Station, Saint Lawrence River (Québec)Infrastructure
27 Nov 2026
GovMarket
We do the hard work.
You win the work.
We find the tenders, read the documents and track who wins, so your time goes on bids you can win.
–open energy and environment tenders right now
–new in the last 7 days
–contracts awarded in the last 12 months
7 days free, then $59/CAD per month
Revenue from government work$312K won so far