Refurbishment Design of Violet Grove Transfer Station by Latitude Engineering for Brazeau County
Awarded 30 Jan 2025
About
Brazeau County awarded a contract to Latitude Engineering for the refurbishment of the Violet Grove Transfer Station.
The project includes redesigning the failing retaining wall with proper drainage, designing a concrete pad for garbage bins beyond the existing footprint, providing cost estimates for wall replacement and anchoring, investigating options for relocating appliance and metal bins for over-side access, planning the removal and replacement of the bin roof structure with adequate height for roll-off operations, raising the asphalt pad to address settlement and drainage issues, and assessing other site layout options to improve efficiency and minimize windblown waste and wildlife access.
The contract value is CAD 43,950.