Asphalt Mill & Inlay and Concrete Upgrades on Arterial Roads in St. Albert
Awarded 15 May 2026
About
The City of St.
Albert awarded a contract to Standard General Edmonton - A Division of Colas Western Canada Inc.
for asphalt milling and inlay, concrete asset replacement, utility adjustments, and landscaping on select arterial roadways in St.
Albert, valued at CAD 1,422,226.46.
The scope included removal and replacement of sidewalks, curb and gutter, driveway aprons, and medians; milling and paving with HT mix designs; removal and replacement of utility frames, covers, and slab tops; and grassed area restoration.
Project management requirements included weekly meetings, KPI reporting, stakeholder communication, and permit acquisition.