Twinning of Highway 63:12 from Mildred Lake to Mildred Lake North Gate
Awarded 30 Apr 2026
About
Alberta Transportation and Economic Corridors awarded a contract to Ledcor Highways Ltd.
for the twinning of Highway 63:12 from Mildred Lake to Mildred Lake North Gate, including grading, granular base course, asphalt concrete pavement, and other work.
The scope covers roadway work from kilometre 30.930 to 40.307 (NBL) and kilometre 35.260 to 40.307 (SBL), involving approximately 279,530 tonnes of aggregate supply (Dept.
Source Option), 23,520 tonnes of aggregate supply (No Dept.
Source Option), 747,760 cubic metres of common excavation, 307,400 cubic metres of borrow excavation (Dept.
Source), 211,600 tonnes of granular base course (Des.
2 Class 25), 10,300 square metres of cold milling asphalt pavement, 24,530 tonnes of Superpave asphalt concrete pavement (Mix Type 100-F-12.5, PG64-34), 60,230 tonnes of Superpave asphalt concrete pavement (Mix Type 100-F-20, PG64-34), and 176,100 cubic metres of common and/or borrow excavation loaded to trucks (Zone 1 Glacial Till).
Bridge files BF85465N-1 and BF85467S-2 include 2,901 square metres of mechanically stabilized earth walls, 510 metres of drilled pile installation, 1,273 cubic metres of concrete, 221,625 kilograms of reinforcing steel, a lump sum for structural steel supply, fabrication, delivery, and erection, and 340 tonnes of asphalt concrete pavement (Mix Type H2, PG 58-28).
Instrumentation and slope monitoring equipment at two locations are also included, with the contractor supplying all.
The contract value is CAD 95,332,968.52.