Bridge Culvert Installation and Liner Work on Highway 584 West of Bearberry
Awarded 17 Apr 2026
About
Alberta Transportation and Economic Corridors awarded a contract to Prentice Creek Contracting Ltd.
for bridge culvert installation, culvert liner installation, and other work on Highway 584 over an unnamed watercourse west of Bearberry, from kilometre 2.674 to 2.938.
The work includes a lump sum for traffic accommodation for bridge construction, structural excavation, supply of 35 metres of 2.4-metre diameter CSP with couplers, supply and install of 57 metres of 914 mm diameter S.W.S.P.
culvert liner, and roadway work, with the contractor supplying all materials.
Valued at CAD 756,940, the contract is scheduled for completion by August 31, 2026.