Bridge Rehabilitation and Deck Waterproofing on Highway 507:02 over Mill Creek
Awarded 21 Mar 2025
About
Alberta Transportation and Economic Corridors awarded a contract to EllisDon Construction Services Inc.
for bridge rehabilitation on Highway 507:02 over Mill Creek, including deck waterproofing, asphalt concrete pavement, deck joint replacement, bridge painting, and other work.
The scope includes removal and disposal of existing deck joint assemblies, supply and installation of Type 1 strip seal deck joint assemblies, surface removal of bridge deck and approach slabs, ultrasonic impact treatment of isolated bottom flange cover plate end termination welds, environmental protection, isolated steel girder overcoating repairs, and bearing recoating.
The contract value is CAD 2,140,770, with a completion date of September 30, 2025.