Construction of Precast Concrete Girder Bridge over Monitor Creek on Highway 886:08

Awarded 03 May 2024

View live tenders
Awarded03 May 2024
Value$1,976,110.00
ProvinceAlberta
CategoryInfrastructure
Ended 2y 6mo ago27d term
Awarded 3 May 2024Expired 30 May 2024

Alberta Transportation and Economic Corridors awarded a contract to Formula Alberta Ltd.

for the construction of a precast prestressed concrete girder bridge over Monitor Creek on Highway 886:08, 15 km south of Consort, Alberta, including demolition of the existing bridge structure and other work.

The contract, valued at CAD 1,976,110, covers traffic accommodation, site isolation, demolition and disposal, structural excavation, supply and driving of galvanized and plain steel H-piles, abutment and pier construction, concrete supply, heavy rock riprap, supply and erection of precast concrete units, waterproofing, asphalt concrete pavement, and roadway work.

Completion is scheduled for October 31, 2024.

Similar open tenders12

Major Bridge Design for Four Alberta Highway Crossings (Ponton River, Melito Creek, Kemp River, CNR Railway)Infrastructure
24 Nov 2026
Bridge Replacement on Highway 547 over WID Irrigation Canal near Arrowwood – Southern Region (Alberta)Infrastructure
19 Nov 2026
Bridge Rehabilitation – Highway 13 over CPKC, WetaskiwinInfrastructure
25 Nov 2026
Bridge Rehabilitation – Hwy 88 over Wabasca River (Km 51.445), Peace RegionInfrastructure
16 Dec 2026
Bridge Rehabilitation – Highway 49 over Spirit River at West Boundary of Rycroft (km 34.437)Infrastructure
17 Dec 2026
Construction Administration & Site Inspection for Highway No. 3 Bridge Replacement over Sturgeon River (west of Prince Albert)Infrastructure
23 Nov 2026
Design and Construction Consultancy for Culvert Replacement on Hwy 88:04 near Slave Lake and Hwy 2:44 near Island LakeInfrastructure
26 Nov 2026
Construction Administration for Highway No. 8 Bridge Replacements over Bighorn Brook and Spruce Creek – Saskatchewan Ministry of HighwaysInfrastructure
30 Nov 2026
Engineering Consultant Services for Culvert and Bridge Replacements on Highways near Nordegg, Sundre and Didsbury, AlbertaInfrastructure
11 Dec 2026
Construction of Three-Span Precast Concrete and Steel Bridge (27 m x 8.53 m) – Big River, SKInfrastructure
20 Nov 2026
Culvert Replacement and Engineering Services for HWY 756 (Prentice Creek), HWY 761 (Blueberry Creek & Tributary to Wilson Creek), and HWY 22 (Cattlepass) – Alberta TransportationInfrastructure
19 Nov 2026
Bridge Replacement Carrying HWY 842 over Bow River (NE 9-21-21-W4M) – Alberta Transportation RFPInfrastructure
07 Dec 2026

GovMarket

We do the hard work.
You win the work.

We find the tenders, read the documents and track who wins, so your time goes on bids you can win.

–open infrastructure tenders right now
–new in the last 7 days
–contracts awarded in the last 12 months
7 days free, then $59/CAD per month

You're In — Free Trial Activated

You now have full access to GovMarket Premium for 7 days. You’ll be charged at the end of the trial unless you cancel.

  • Tell Us What You Do — We'll surface the tenders that are most relevant to your business.