Bridge Superstructure and Abutment Substructure Replacement on Highway 1:04 Near Mini Thni
Awarded 28 Nov 2025
About
Alberta Transportation and Economic Corridors awarded a contract to ERK Construction Inc.
for the replacement of the bridge superstructure and abutment substructure on Highway 1:04 at BF 74600W, carrying Highway 1 westbound over Bear Hill Road near Mini Thni (formerly Morley), from kilometre 22.194 to 22.194 (WBL) in the Southern Region.
The work includes a lump sum for traffic accommodation for bridge construction, 26 piles for pile set-up (driven piles), 18 piles for drill rig set-up (drilled piles), a lump sum for precast concrete units (10.0m SLC-510 – Interior) including supply, fabrication, delivery, and erection, 25,352 kilograms of corrosion-resistant reinforcing steel supply, 150 cubic metres of Class HPC concrete supply and place, 91 cubic metres of Class C concrete supply and place, and a lump sum for roadway work, with the contractor supplying all materials.
The contract value is CAD 5,341,692.40, and the completion date is October 31, 2026.
Similar open tenders12
Other similar contracts12
GovMarket
We do the hard work.
You win the work.
We find the tenders, read the documents and track who wins, so your time goes on bids you can win.